Compute

Data Centres & Colocation

Somewhere secure, powered and connected for your servers: from a single rack for your WMS to liquid-cooled AI racks and containerised units at the depot.

Resilience

Uptime tiers: maximum expected downtime per year

Tier I (99.671%)≈ 28.8 hours
Tier II (99.741%)≈ 22.7 hours
Tier III (99.982%)Concurrently maintainable≈ 1.6 hours
Tier IV (99.995%)Fault tolerant≈ 26 minutes
Uptime Institute tier classification. Many facilities say they are "built to Tier III" without formal certification. Ask which applies.

Choose an option

Pricing is mostly about power

Colocation is now priced mainly per kilowatt of contracted power. Space, cooling and a share of the building's resilience are bundled in. Cross-connects, remote hands and extra power are often billed separately.

Location matters

Slough and West London are the best connected but the most grid-constrained. Manchester, Edinburgh and South Wales can be cheaper and have more power available. For logistics, a site near your hubs and fibre routes can matter more than the headline rate.

What to include in a request

  • IT load now and in 2–3 years (kW)
  • Rack count and density
  • Cooling: air, rear-door or liquid
  • Connectivity and cloud on-ramps
  • Term and start date
Worked example

Why PUE shows up on your bill

Power usage effectiveness (PUE) is total facility power divided by IT power. A PUE of 1.4 means every 1 kW of servers needs 0.4 kW more for cooling and losses. Many colocation contracts recharge power at metered usage × PUE, or price it into a per-kW rate.

100 kW of IT running all yearPUE 1.2PUE 1.4PUE 1.6
Total energy1,051 MWh1,226 MWh1,402 MWh
Cost at 24p per kWh≈ £252k≈ £294k≈ £336k
Emissions at 0.131 kgCO₂e/kWh≈ 138 t≈ 161 t≈ 184 t

Calculated: 100 kW × 8,760 hours × PUE. Grid factor: DESNZ 2026 (location-based).

Indicative prices
ServiceTypical rangeUnitBasis
Colocation power, UK retail£185–£380per kW per monthExcl. VAT. Cross-connects and remote hands usually extra
Standard rack, regional UK£800–£1,500per rack per monthExcl. VAT; power allowance varies
Full cabinet, Slough or London Docklands£1,600–£3,800per cabinet per monthExcl. VAT; power allowance varies
Cross-connect£150–£480per connection per monthExcl. VAT
High-density racks, 20–50 kW£230–£340per kW per monthExcl. VAT; contracted power
Liquid-cooled, 50 kW+£300–£420per kW per monthExcl. VAT; contracted power
30 kW liquid-cooled rack£2,000–£5,000per rack per monthExcl. VAT; London highest, regions lower
Wholesale / powered suite, 1 MW+£60–£150per kW per month5–15 year terms; strongly location and power dependent
Containerised data centre moduleFrom £90,000per module (from)Excl. IT, groundworks and grid connection

Planning benchmarks, not quotes. As of November 2026. Excludes VAT unless stated.

How we estimate carbon here

We use 0.131 kgCO₂e per kWh (UK grid electricity (location-based), DESNZ GHG conversion factors 2026), multiplied by the electricity your quote covers. Renewable contracts and PPAs can lower the market-based figure. It is an estimate for comparison, not a verified figure. Read the methodology.

Buy, own, rent, lease or contract?

Ways to get data centres

Contract

12–36 months retail, 5–15 years wholesale

Opex, committed

Watch: Take-or-pay commitments, early-exit fees and indexation clauses. Match the term to how sure you are of demand.

Build & own

Only at very large scale with a secured grid connection

Capex, long-term

Watch: Grid-connection lead times, planning consent, construction risk and the skills to operate it.

How to choose

Also in Compute

Frequently asked questions

Is high-density more expensive?

Per rack, yes. Per kW it is often similar or lower, because fixed costs are spread over more power.

How long does it take to get space?

Standard racks can be ready in weeks. High-density and MW-scale capacity can take months, depending on power availability.