Energy Assets: Solar, Batteries, Charging & Backup

Generate, store and deliver power on your own sites: solar on warehouse roofs, batteries, depot chargers for electric fleets, backup power and grid connections.

Order of works

A sensible order for depot energy projects

  1. 1
    MeasureFirst

    Sub-meter loads and get half-hourly data.

  2. 2
    Cut wasteQuick wins

    Lighting, controls, out-of-hours loads.

  3. 3
    Check grid capacityBefore buying kit

    Know your agreed capacity and headroom.

  4. 4
    Add solar and storageSelf-supply

    Size to your daytime load and roof.

  5. 5
    Electrify fleet and heatThen

    Chargers and heat pumps, managed to the connection.

Measuring first avoids oversizing chargers, batteries and connections.

Choose an option

Warehouse roofs are power stations

A large distribution-centre roof can host hundreds of kilowatts of solar, generating cheap power in the hours when conveyors, lights and chargers run. Batteries carry it into the evening and peak periods.

Start with the grid connection

Chargers, data rooms and automation can quickly outgrow your supply. Check your connection capacity early, because upgrades can take months or years.

Ways to pay

  • Buy outright and claim capital allowances
  • No-capex PPA: a provider owns the system and sells you the power
  • Lease or asset finance
  • Charging- or energy-as-a-service for a monthly fee
  • Hire for temporary or emergency needs
Connecting to the grid

G98 or G99? The paperwork for on-site generation

ProcessApplies toWhat happens
G98Small systems up to 16 A per phase (about 3.68 kW single-phase or 11.04 kW three-phase)Install, then notify the DNO within 28 days
G99Anything larger, including most commercial solar and batteriesApply to the DNO and get approval before connecting
Export limitationSites where the network has little capacityAn export limit lets you install more without network upgrades

Source: Energy Networks Association engineering recommendations G98 and G99.

Indicative prices
ServiceTypical rangeUnitBasis
Commercial rooftop solar, installed£700–£1,100per kWpExcl. VAT; falls with system size
500 kWp warehouse roof system£350,000–£550,000per systemExcl. VAT and roof remediation
Commercial battery, installed£350–£700per kWh usableExcl. VAT; larger systems cheaper per kWh
Grid-service revenue via aggregator£30–£90per kWh per yearSystems over ~100 kWh; shared with aggregator
22 kW AC charger, installed£1,800–£3,500per socketExcl. VAT, grid upgrades and grants
50 kW DC rapid charger£14,000–£35,000per unitInstalled; excl. VAT and grid upgrades
150 kW DC charger (HGV depot)£45,000–£80,000per unitInstalled; excl. VAT and grid upgrades
10-truck HGV depot, all-in£650,000–£1,400,000per siteEquipment, civils, HV connection and load management
Generator hire, SME sizes£40–£150per dayWeekly and monthly hire cheaper per day; fuel extra
Industrial generator hire, 200 kVA+From £500per day (from)Delivery, fuel and installation extra
Small commercial connection£500–£3,000per connectionExcl. VAT; 5–20 working days typical
Medium commercial connection£2,000–£15,000per connectionExcl. VAT
HV connection to major reinforcement£50,000–£2,000,000per projectHighly site-specific
Sub-metering and monitoringQuoted on requestper siteDepends on meter count and software

Planning benchmarks, not quotes. As of November 2026. Excludes VAT unless stated.

How we estimate carbon here

We use 0.131 kgCO₂e per kWh (UK grid electricity (location-based), DESNZ GHG conversion factors 2026), multiplied by the electricity your quote covers. Renewable contracts and PPAs can lower the market-based figure. It is an estimate for comparison, not a verified figure. Read the methodology.

Buy, own, rent, lease or contract?

Ways to get energy assets

Buy

Best lifetime value, tax reliefs

Capex

Watch: Upfront capex, depreciation and obsolescence. You still need space, power, cooling and people to run it.

Build & own

Self-develop larger solar, storage or private wire

Capex, long-term

Watch: Grid-connection lead times, planning consent, construction risk and the skills to operate it.

Lease or finance

Spread cost monthly

Opex or capex, monthly

Watch: Know whether it is an operating (FMV) or finance lease, what happens at end of term, and who carries residual-value risk.

Contract

PPA or as-a-service, no capex

Opex, committed

Watch: Take-or-pay commitments, early-exit fees and indexation clauses. Match the term to how sure you are of demand.

Hire

Temporary, emergency or seasonal

Opex, flexible

Watch: Delivery and collection charges, minimum hire periods and fuel or consumables.

How to choose

Also in Energy

Frequently asked questions

Can we put solar on a leased warehouse?

Often yes, with landlord consent. A PPA or a landlord-tenant agreement can share the savings.

Are there grants?

The Depot Charging Scheme part-funds depot chargers for fleets with electric vans, HGVs or coaches when a window is open. Other savings come from tax reliefs.