Depot EV Charging for Vans & HGVs

Chargers at your depot for electric vans and trucks, owned outright or provided as a service, sized to your shifts and grid connection.

Charging speed

Time to add 100 kWh at different charger powers

22 kW ACMany vans accept only 11 kW AC≈ 4 h 30 min
50 kW DC≈ 2 h
150 kW DCTypical HGV depot charger≈ 40 min
350 kW DC≈ 17 min
1 MW (MCS)Megawatt Charging System, for HGVs≈ 6 min
Energy ÷ power, ignoring the slowdown near full charge. The vehicle’s own limit often sets the real speed.

Depot charging does most of the work

Around 80–90% of electric HGV charging is expected to happen at the depot, overnight or between shifts. Public hubs fill the gaps on long routes.

Plan in this order

  • Duty cycles and dwell times for each vehicle
  • Grid capacity and upgrade lead time
  • Charger mix: AC for vans, DC for trucks
  • Load management, batteries and solar
  • Funding: grant, buy, lease or charging-as-a-service

Charging-as-a-service

Some providers install and operate chargers at your depot with no upfront cost and charge per kWh or per month. Some also let you sell spare capacity to other fleets.

How it serves your logistics network

  • Charge electric vans overnight
  • Run electric HGVs on trunking routes
  • Share spare depot capacity with other fleets
Worked example

Energy and emissions for 20,000 km a year in a van

Electric vanDiesel van
Energy used≈ 5,000 kWh (0.25 kWh/km)≈ 1,600 litres (8 l/100 km)
Emissions≈ 0.66 tCO₂e (UK grid)≈ 4.1 tCO₂e
LicenceCategory B up to 4,250 kg for alternatively fuelled vansCategory B up to 3,500 kg

Illustrative consumption. Factors: DESNZ 2026 (grid 0.131 kgCO₂e/kWh, diesel 2.58 kgCO₂e/litre).

Indicative prices
ServiceTypical rangeUnitBasis
22 kW AC charger, installed£1,800–£3,500per socketExcl. VAT, grid upgrades and grants
50 kW DC rapid charger£14,000–£35,000per unitInstalled; excl. VAT and grid upgrades
150 kW DC charger (HGV depot)£45,000–£80,000per unitInstalled; excl. VAT and grid upgrades
10-truck HGV depot, all-in£650,000–£1,400,000per siteEquipment, civils, HV connection and load management

Planning benchmarks, not quotes. As of November 2026. Excludes VAT unless stated.

How we estimate carbon here

We use 0.131 kgCO₂e per kWh (UK grid electricity (location-based), DESNZ GHG conversion factors 2026), multiplied by the electricity your quote covers. Renewable contracts and PPAs can lower the market-based figure. It is an estimate for comparison, not a verified figure. Read the methodology.

Buy, own, rent, lease or contract?

Ways to get depot charging

Buy

With grant support and a long depot lease

Capex

Watch: Upfront capex, depreciation and obsolescence. You still need space, power, cooling and people to run it.

Lease or finance

Spread hardware cost

Opex or capex, monthly

Watch: Know whether it is an operating (FMV) or finance lease, what happens at end of term, and who carries residual-value risk.

Contract

Charging-as-a-service, no capex

Opex, committed

Watch: Take-or-pay commitments, early-exit fees and indexation clauses. Match the term to how sure you are of demand.

How to choose

Typical offers we request quotes from

Supplier names stay private until you choose a quote. One request goes to the suitable suppliers for your route, location and needs.

Offer A

Fleet electrification provider

Depot electrification on a financed model

Indicative price
Monthly, no upfront capex
Timing
Months; grid-dependent
Coverage
UK-wide
  • Chargers, batteries and power
  • Operated for you
  • HGV and bus experience
Request this quote
Offer B

HGV charging specialist

Depot Charging as a Service

Indicative price
Per kWh or monthly
Timing
Months
Coverage
UK-wide
  • No upfront capex
  • Sell spare capacity to other fleets
  • Fleet card payments
Request this quote
Offer CBuy

Fleet charging installer

High-power DC charging for logistics depots

Indicative price
150 kW DC ~£45k–£80k each
Timing
Months; grid-dependent
Coverage
UK-wide
  • 100–400 kW DC
  • Multi-site delivery
  • Grant support
Request this quote

Offers describe the types of supplier we invite to quote. Prices are indicative and subject to supplier confirmation, availability and terms.

More in energy assets

Frequently asked questions

How big a grid connection does an HGV depot need?

It depends on charger power and shifts. Ten trucks on 150–200 kW DC chargers can need 1–3 MVA; slower overnight charging needs much less. A survey will confirm.